Average processing time for local applications
Source: Department for Infrastructure, Northern Ireland planning statistics, April to June 2026 (provisional), published 22 October 2026. The official “average” is a median, and the target for local applications is 15 weeks.
| Council | Apr–Jun 2026 (weeks) | Apr–Jun 2025 (weeks) | Full year 2025/26 (weeks) |
|---|---|---|---|
| Fermanagh and Omagh | 8.4 | 7.6 | 7.6 |
| Mid and East Antrim | 10.6 | 7.0 | 7.6 |
| Antrim and Newtownabbey | 11.4 | 10.4 | 13.0 |
| Derry City and Strabane | 17.3 | 34.5 | 25.2 |
| Ards and North Down | 18.0 | 17.6 | 16.3 |
| Mid Ulster | 18.0 | 19.2 | 22.4 |
| Lisburn and Castlereagh | 18.3 | 48.0 | 29.4 |
| Belfast | 18.8 | 13.6 | 18.1 |
| Causeway Coast and Glens | 20.8 | 23.0 | 18.2 |
| Armagh City, Banbridge and Craigavon | 21.8 | 20.2 | 21.8 |
| Newry, Mourne and Down | 45.8 | 46.1 | 45.8 |
| Northern Ireland | 20.0 | 19.8 | 19.6 |
What stands out
- Only three councils were inside the 15-week target: Fermanagh and Omagh, Mid and East Antrim, and Antrim and Newtownabbey.
- Derry City and Strabane and Lisburn and Castlereagh both improved sharply on a year earlier.
- Newry, Mourne and Down remained by far the slowest, with about 4% of local applications decided within 15 weeks.
- Speed is not the same as approval. Mid and East Antrim decided quickly but approved 81% of local applications in the quarter, the lowest rate in Northern Ireland, against 94% overall.
What the figures cannot tell you
They are medians across all local applications, from small extensions to complex rural and commercial schemes. They also include withdrawn applications. A complete application with no consultee issues can move faster than the median; one that needs surveys, amended drawings or committee consideration can take much longer.
Practical advice
- Build realistic timescales into any purchase, finance or building programme.
- Submit a complete application. Missing information is the easiest delay to avoid.
- In slower councils, think about pre-commencement conditions early so you can start promptly once permission arrives.
Source: DfI planning activity statistics.